1)
Will the university accept a cloud-hosted simulation-management and recording platform using on-campus capture equipment, and will it consider a software-only partial award with hardware installation and commissioning delivered under a separate university contract?


We will accept a cloud-hosted solution as long as it fits all requirements set forth by the RFP. We would consider it but would need to know who supports which aspects and all the details as to how the hardware to software relationship is handled. Feel free to propose all possible options.


2)
Please identify the simulator and patient-monitor manufacturers, models, software versions, and available integration interfaces for all six labs, and clarify whether synchronized simulator-data recording requires structured numeric/event telemetry, a recording of the monitor display, or both, including any required synchronization tolerance?


We use a mix of Laerdal and Gaumard simulators and their respective applications for patient monitors. We have Leardal SimMan ALSs, juniors, nursing ann, mama ann, sim mom, and then Gaumard we have super tory. We are really looking for a device capture of the patient monitor all in one that we will be using. We use dell all in one (AIO) computers mounted to the wall running either Laerdal’s Patient monitor software or Gaumards Gaumard vitals software. The AIO computers we use have HDMI and Display Port ports.


3)
Please provide the expected numbers of faculty, student and administrator users; peak concurrent remote viewers; recording hours per lab per day; required recording retention period; and the volume and format of any existing recordings or assessment records requiring migration?


We currently have 500 users, but I would say a max of 1000 users to be entered into the system. If this is a variable the changes pricing or scale, this may be a topic discussed in further detail before a decision is made. Our lab would maybe record 5 hours a day but then some days we may record 8 hours a day. Our desired retention period would be 3 years, but we would want to be able to change expirations date to save certain things past 3 years. We currently have 2.7TB of videos with our current solution.


4)
What initial contract term and renewal options should vendors price, and will the university accept equipment-inclusive annual subscription pricing with an agreed mechanism for recovering unamortized equipment costs upon early termination, considering Sections 4.2, 4.4, and 4.10?


The university intends to purchase all required equipment outright and is not seeking an equipment-inclusive contract as such. Vendors may separately price any required software, licensing, support, or service subscriptions, including applicable terms and renewals. Alternative subscription-based pricing models may be proposed for consideration, but the University makes no commitment to accept them.


5)
Please provide the required installation, production go-live, and acceptance milestones, and clarify whether HECVAT and VPAT documentation must be submitted with the proposal or after award, given the differing instructions in Sections 4.42, 4.47, 5.1, and 6?


We have roughly a year timeline so we will set milestones based on that time frame. The most important part and a hard deadline is the go live date. We would like everything up and running at least 2 weeks before the opening of the new lab space. Additional to this we would need access to the software as soon as possible to become familiar with it. As to the HECVAT and VPAT requirement, what is noted in Section 6 prevails, however we are happy to accept that documentation with the proposal submission.

Vendor 2 of 3

1)
There was mention of re-use of the current cameras and other solution equipment. What are the current cameras and other solution equipment that you would like to potentially reuse?


We currently use axis cameras and audio Technica microphones. Ideally, we would want to use all new equipment unless the cost makes this impossible. Please include in your proposal NEW equipment. Our needs have changed and would like proposals to include all new equipment. Disregard the reuse of current equipment.


2)
Next, it was mentioned that the system should have a backup job or the ability to recover data/videos in the event something happens to a recording. We can provide a redundant server in our quote if that is needed, or would the university want to do backups to local storage or a NAS? Any further information you can share there is greatly appreciated so we can build out the quote appropriately with our RFP submission.


Please provide pricing and build out with the redundant server option. We would need to know how the backup job is conducted on your end to determine if we can host this on university hardware.

Vendor 3 of 3

1)
Do you have a need to page overhead into the sim rooms from the control rooms. “Voice of God’ overhead or two-way communication between the sim room participants and the control room?


We would like to have the feature in case our in-room audio fails or we want to send a preprogrammed command for students to start or for time warnings. We are not expecting this to be a feature that is included within the observations software but if it is built in to the observation platform then please include it in the cost. Ideally, we would like to see proposals with and without the two-way communication between the sim room participants and the control room from just the Observation platform.

2)
In the Sim OR room do you expect to use additional medical equipment with video output that needs to be captured into the software?


No.


3)
Do you have a need for video and/or audio capture in the sink hallway?


No.


4)
Do you have a need for video and/or audio capture of the debriefings?


We would like for this to be possible but the debrief capture units would need to be mobile solutions.


5)
Can you clarify the specification of "Check in students to automatically start recordings"?


We would like for our standardized patient graduate sims to be able to run with out faculty. We would like for students to essentially schedule when they want to do their sim and then they can “check in� and then the recording would start automatically.


6)
Can you clarify or give example of "Alter assignments after they have started or been recorded"?


This means that we may need to change details on a rubric or scoring after its recorded and this is a feature that we would want to have. The assignment and scoring can not be locked once created.


(End.)